20/08/2017 - Initial Deposit paid to New Living Homes to book the Land and House Package.

19/09/2017 - 10% of Land paid to Marsdens Law Group (Dart West Developments).

07/10/2017 - 5% of House paid to New Living Homes.

07/10/2017 - Building Contract and Tender Signed.

28/10/2017 - Colour Selections done for Joinery, Interior and Exterior.

08/11/2017 - Contracts exchanged with other Solicitor.

15/01/2018 - Stamp Duty for Land paid to Office of State Revenue.

17/04/2018 - Land Registered under Deposited Plan.

24/04/2018 - Formal Approval received from the Bank

14/05/2018 - Land Settlement.

07/06/2018 - CDC Lodged with Camden Council by the builder. 

19/06/2018 - First Home Buyer Grant Approved.

06/07/2018 - CDC approved by Camden Council.

10/07/2018 - Validation Letter received from the builder.

12/07/2018 - Letter of Commencement (LOC) received from the Bank.

08/08/2018 - Released for Construction.

18/08/2018 - Excavation completed. 

 